Judgment record
CAFCA Limited v Patrick Chikuyo
[2013] ZWLC 185LC/H/185/20132013
Viewing: Word Document (Legacy)
Loading document...
Full text archive
Judgment text copy
A clean reading copy is shown below. Use Download for the original formatted document.
IN THE LABOUR COURT OF ZIMBABWE JUDGMENT NO. LC/H/185/2013
HELD AT HARARE ON 16 MAY, 2013 CASE NO. LC/ H/218/2012
In the matter between
CAFCA LIMITED – Appellant
And
PATRICK CHIKUYO – Respondent
Before The Honourable L. Matanda-Moyo, President
For Appellant - W. Magaya(Legal Practitioner)
For Respondent - B. Makururu (Legal Practitioner)
MATANDA-MOYO, L.
This is an appeal against the determination by the NEC for the
Engineering and Iron and Steel Industry which ordered that the Respondent be
reinstated and that a warning letter be withdrawn and that the deductions
made be reimbursed.
Both parties conceded that the order for reinstatement was incompetent
as Respondent was never dismissed from work. Such concession was properly
made.
Appellant filed its grounds of appeal as follows;
JUDGMENT NO. LC/H/185/2013
1) That the NEC failed to appreciate the issues at hand. The issue was not
criminal responsibility but that of worker’s responsibility towards assets
of the company.
2) That the NEC erred in failing to appreciate that the Respondent as the
Head of Department had the responsibility for safekeeping of company
tools and had responsibilities to put in place measures to safeguard
company assets and maintain a proper inventory of such assets. It was
Respondent’s responsibility to devise and implement measures for the
access and use of the tools and their safekeeping Appellant prayed that
the decision of the NEC be set aside and that the decision of Works
Council be upheld.
The Respondent filed a notice of response wherein he challenged the
appeal as being improperly before the Labour Court. The Respondent
submitted that an appeal from a decision of the NEC Appeal Committee lies to
the General Engineering Committee. It is the decision of the General
Engineering Committee which is appealable to this court. The Respondent also
challenged the appeal process. He submitted that Appellant is challenging the
gross unreasonableness of the NEC’s decision. Appellant therefore used the
wrong procedure. It should have noted a review application as opposed to an
appeal. The Respondent also submitted that the Appellant should not be heard
as it has not complied with the decision it is appealing against.
The Appellant responded on the issue of the jurisdiction of this court by
submitting that the NEC Appeals Committee had powers to hear an appeal
from the Works Council. Appellant in its Heads of Argument argued that the
2
JUDGMENT NO. LC/H/185/2013
NEC Appeal Committee is the same as the General Engineering Committee. It
argued that the appeal was properly before this court. On the date of hearing
Appellant argued that the NEC had no jurisdiction to hear an appeal from the
Works Council. Counsel for the Appellant argued therefore that the decision of
the NEC was null and void. Such ground of appeal was raised for the first time
during the appeal. It is trite that parties should disclose to each other the
grounds or argument to be relied upon by such parties. Court proceedings are
not a game of hide and seek. Both parties should come to court aware and
prepared to argue the case.
It is common cause that the Appellant subjected itself to the jurisdiction
of the NEC. Appellant never challenged NEC’s jurisdiction to hear the appeal.
Appellant has approached this court as an appeal court. The issue of the
jurisdiction of the NEC was never placed before the NEC for it to make a
determination. It is unacceptable for such an issue to be placed before an
appeal court. NEC could have dealt with such a ground had it been raised.
Section 7(3) of Appellant’s Code of Conduct provides;
“subject to the provisions of any law which may provide for an aggrieved party to have
recourse to appeal to a recognized legal authority, the decision of the Cafca Works Council
shall be final.”
It is correct that an appeal from the Works Council lied to this court and
not the NEC. However because the Appellant acquiesced to having the matter
being heard by the NEC Appeals court, he is barred to raise the issue of
jurisdiction at this stage.
3
JUDGMENT NO. LC/H/185/2013
Once the parties had agreed to have the matter determined by the NEC
Appeals Committee it followed that any appeal arising from the decision of the
NEC Appeals Committee had to be referred to the General Engineering
Committee. The Appellant therefore jumped the gun in filing an appeal directly
to this court. Appellant has also failed to reasonably explain his reasons for
failing to exhaust the domestic remedies. See Olivine Industries (pvt) Limited
vs Gwekwerere SC63/05.
Accordingly I am satisfied that the appeal is improperly before me and is
hereby dismissed with costs.
Coghlan,Welsh and Guest– Appellant’s Legal Practitioners
Guni and Guni – Respondent’s Legal Practitioners
4