Judgment record
Kenneth Chiguvare v Maffack Asset & Fund Managers (Private) Limited
HH 124-2012HH 124-20122012
Viewing: Word Document (Legacy)
Loading document...
Full text archive
Judgment text copy
A clean reading copy is shown below. Use Download for the original formatted document.
1
HH 124-2012
HC 10764/04
KENNETH CHIGUVARE
versus
MAFFACK ASSET & FUND MANAGERS (PRIVATE) LIMITED
HIGH COURT OF ZIMBABWE
PATEL J
Civil Trial
HARARE, 25 to 27 October 2011 and 19 March 2012
N.D. Munharira, for the plaintiff
M.T. Maja, for the defendant
PATEL J: This is a property dispute emanating from an
agreement of sale concluded between the parties in September 2003.
The plaintiff’s claim, as amended, is for damages in the sum of US$63,000
(being the cost of obtaining a similar property) or repayment of the sum
of US$42,000 (being the total amount paid by the plaintiff to the
defendant).
The issues for determination were revised at the commencement
of the trial. They are as follows: (i) whether it was the plaintiff or the
defendant who breached the agreement of sale; (ii) which party was
entitled to cancel the agreement of sale; (iii) whether the defendant is
liable to pay the plaintiff on either of his claims; and (iv) whether the
defendant is entitled to retain the sums paid by the plaintiff as pre-
estimated damages.
The Evidence
Sam Chiguvare represented the plaintiff under a general power of
attorney. His evidence was as follows. The agreement of sale for the
property in question was concluded on18 September 2003. The agreed
2
HH 124-2012
HC 10764/04
purchase price was ZW$92,147,000 in respect of the land and the
construction of a cluster house in conformity with clause 14.2 of the
agreement. The purchase price was subject to construction cost
escalation, payable by the plaintiff before registration of transfer. In
terms of clause 14.6 of the agreement, barring any supervening
impossibility, the defendant undertook to complete construction in or
before June 2004 or any other date thereafter agreed between the
parties. The initial deposit of ZW$6,000,000 and the sum of
ZW$21,536,750 (25% of the balance due) were paid on or before
signature. The 75% balance of ZW$64,610,250 was payable in 12 monthly
instalments. He stopped paying in April 2004 because there was no
progress on construction. He only saw a road and the sewage trenches.
At that stage, he had paid a total of ZW$58,536,774 being about two-
thirds of the purchase price. He did not make any written complaint but
advised the defendant’s representative (Lovemore Mafutah) regarding
the cessation of payments. The agreement provides for the payment of
interest and the submission of monthly statements showing the
instalments due and the interest rates applicable. Mafutah did not
furnish any such statements at the relevant time. The plaintiff’s claim for
US$63,000 is based on a valuation report (compiled by Empire Properties)
in respect of a similar sized property in the same area, with the same
style and size of cluster house. As he had only paid two-thirds of the
purchase price, he withdrew his claim for US$63,000 and persisted with
the claim for US$42,000. This sum was also equivalent to the total paid in
Zimbabwe Dollars at the exchange rate prevailing in 2003 and 2004.
Under cross-examination, the plaintiff accepted that by the end of
April 2004 he should have paid 7 instalments totalling ZW$37,689,312
plus interest and that he had paid only ZW$31,000,024 at that time.
3
HH 124-2012
HC 10764/04
Nevertheless, his primary objective was to complete full payment within
12 months. He also maintained his denial of having received any monthly
statements until May 2004, after he had reported the matter to the
police, which lead to Mafutah’s arrest.
Lovemore Mafutah is a Director of the defendant company. His
evidence was that the plaintiff was to pay ZW7,000,000 per month. This
was verbally agreed but not recorded in the agreement of sale itself. The
witness attempted to explain the interest clause in the agreement as
requiring the payment of 30% interest on the outstanding monthly
balance. The plaintiff’s payments after signature were always late and did
not equate to the agreed monthly amount of ZW$7,000,000. His lawyers
wrote to the plaintiff on 26 May 2004 giving him 30 days to rectify his
breach, in terms of clause 7.1 of the agreement. Subsequently, on 10 July
2004, his lawyers wrote to cancel the agreement. Thereafter, he became
entitled to retain the payments already made, as security for damages to
be established, in accordance with clause 7.1.3 of the agreement. At that
stage, the construction completed on the plaintiff’s stand consisted of
sewer and water reticulation pipes. It was not possible to complete the
project because of the plaintiff’s failure to remedy his breach by the
stipulated deadline. The plaintiff’s stand was then sold to a third party in
October or November 2004. The witness stated that he did furnish
monthly statements to the plaintiff. However, he was unable to produce
any copies as these were lost when the case files were moved from his
former lawyers to the current lawyers. The pre-estimated damages in
respect of the plaintiff’s stand amounted to US$5,500. This included the
cost of re-advertising, re-designing and replacing vandalised pipes.
Under cross-examination, he conceded that there was no
reference to the monthly statements or the costs incurred as pre-
4
HH 124-2012
HC 10764/04
estimated damages in the discovered schedule of documents filed by his
erstwhile lawyers in October 2006. He also conceded that as the verbal
stipulation to pay ZW$7,000,000 per month was not reduced to writing,
as required by clause 13 of the sale agreement, the plaintiff was not
bound by it and was only obliged to pay a reasonable amount every
month. When questioned by the Court, he accepted that it would not
have been necessary to fix the monthly payment as the interest clause
would have covered any amount overdue on monthly balances. He
further accepted that by 27 April 2004 the plaintiff had paid a total of
ZW$58,536,774. However, he was not able to say what interest was owed
by the plaintiff as at that date, nor could he explain the interest and other
calculations on the May 2004 statement of account submitted to the
plaintiff.
In 2003 and 2004, he had spent about ZW193,000,000 on the 30
stands comprising the project. He had completed servicing the stands
and they were all equally developed as at 30 June 2004. Therefore, the
amount spent on the plaintiff’s stand would have been just over
ZW$6,400,000. The trial was adjourned to enable the witness to produce
documents supporting the defendant’s claim for pre-estimated damages.
These were then produced in respect of expenses incurred for the whole
project comprising 30 stands, covering the costs of re-advertising, re-
designing and re-planning. The payments were made through the trust
account of his former lawyers. They only submitted reports and kept the
receipts, which could not presently be located.
At the close of the trial, counsel for both parties were directed to
incorporate in their closing submissions the following calculations: (a) the
total amount paid by the plaintiff divided by the total capital and interest
due by the plaintiff under the agreement of sale (in Zimbabwe Dollars)
5
HH 124-2012
HC 10764/04
multiplied by US$63,000; and (b) the total expenditure incurred by the
defendant after April 2004 (calculated in Zimbabwe Dollars and converted
to United States Dollars) divided by 30. Regrettably, neither counsel has
addressed these issues satisfactorily, making it very difficult for the Court
to compute the parties’ respective claims. Indeed, their submissions were
generally inadequate and of very little assistance to the Court.
Who Breached the Agreement of Sale and Who was Entitled to Cancel
Under clause 7.1 of the agreement of sale, the defendant was
entitled to cancel the agreement in the event of the plaintiff failing to
effect any payment due and thereafter failing to rectify any such breach
within 30 days of a written notice calling upon him to do so. It is not in
dispute that the plaintiff duly paid the initial deposit and 25% of the total
balance due on or before signature. The mode of payment thereafter is
stipulated in the agreement as follows:
“The remaining balance shall be paid by 12 monthly
instalments commencing 29 October 2003 and thereafter on or
before the last day of each succeeding month with 3% interest on
monthly balance below the building society lending rate. Should
the Seller finish construction before the end of the twelve (12)
month period the total balance due shall become payable within
fourteen (14) days in terms of clause 5. The Seller shall provide at
the end of each month the instalment due and the interest rate
applicable.”
It is evident that no fixed monthly payment was prescribed in the
agreement itself. In this regard, Mafutah conceded that the verbal
agreement for the plaintiff to pay ZW$7,000,000 per month was
unenforceable and that he was only obliged to pay a reasonable amount
every month. As for interest, it is not at all clear from the agreement how
the interest component was to be calculated at the end of each month.
Mafutah himself could not satisfactorily explain the interest clause, nor
6
HH 124-2012
HC 10764/04
was he able to say what interest was owed as at the end of April 2004. He
could not even explain the interest and other calculations on the May
2004 statement of account submitted by his lawyers to the plaintiff.
The evidence shows that the plaintiff’s payments were somewhat
erratic and not always made at the end of each month. He also admitted
that by the end of April 2004 he should have paid a total of
ZW$37,689,312 plus interest and that he had paid only ZW$31,000,024 at
that time. Nevertheless, his testimony in this respect, which I am inclined
to accept, was that he did not receive any monthly statements showing
the instalment due and the interest rate applicable. He was therefore
unable to determine what specific amount was due at any given time and
was only intent on completing full payment within the agreed period of
12 months.
On these facts, given the imprecision of the agreement between
the parties, it cannot be said that the plaintiff was in breach of his
payment obligations as at the end of April 2004, when he decided to
cease further payments and terminate the agreement. Thereafter, at the
end of May 2004, the defendant’s lawyers wrote to the plaintiff calling
upon him to remedy the shortfall “as projected to June 2004 in terms of
the attached statement”. However, this letter was only written after the
plaintiff had reported the matter to the police and after Mafutah was
arrested. Moreover, by that stage, the plaintiff had already resiled from
the agreement and the threatened cancellation of the agreement within
30 days had consequently become academic. In any event, even if there
was a subsisting right of cancellation, there was no explanation of the
figures contained in the statement relating to the capital and interest
comprising the supposed shortfall of over ZW$70 million. Very
significantly, that explanation was not availed by the defendant even at
7
HH 124-2012
HC 10764/04
the trial of this matter. In the premises, I am unable to find that the
plaintiff breached the agreement at any relevant stage or that the
defendant became entitled to cancel the agreement at any time.
Turning to the plaintiff’s case, his evidence was that he stopped
making further payments after April 2004 because there was no progress
on the construction work on his stand. He only saw a road and the
sewage trenches. The defendant’s evidence was that by the beginning of
July 2004, when his lawyers purported to cancel the agreement, he had
completed the installation of sewer and water reticulation pipes on the
plaintiff’s stand. I do not perceive that these two versions are necessarily
inconsistent. It is perfectly possible that the defendant had installed the
pipes in question in the two months period after the plaintiff had viewed
the stand.
What is more critical is that in terms of clause 14.6 of the
agreement, the defendant undertook to complete construction in or
before June 2004 or any date thereafter agreed between the parties,
subject to any supervening impossibility. On the ground, as at the end of
June 2004, the defendant had not even begun the construction of the
house let alone completed it. It is also pertinent to note that the permit to
subdivide the entire property was only granted by the City of Harare in
January 2005. Thus, the defendant could not have lawfully developed the
30 stands and completed construction work by the end of June 2004. This
further demonstrates that the defendant was not in any position to fulfil
the contract that it had entered into with the plaintiff. There is nothing in
the evidence to show that the parties had agreed to extend the deadline
for completion of construction. Moreover, the defendant has not pleaded
or established any supervening impossibility precluding or frustrating the
fulfilment of its contract with the plaintiff.
8
HH 124-2012
HC 10764/04
One of the difficulties with the plaintiff’s case is that he stopped
making any payment after April 2004, without giving the defendant any
formal warning or written notice of cancellation. He should certainly have
done so in order to safeguard his rights. Again, arguably, he should have
waited until the end of June 2004 before taking any decisive action.
Nevertheless, having regard to the absence of any meaningful
development on the stand as at the end of April 2004, it was obvious that
the defendant was nowhere near completion of construction by June
2004. Given this scenario, it seems to me that the plaintiff was amply
justified in terminating the agreement of sale in view of the defendant’s
anticipated failure to perform its obligations timeously in terms of the
agreement. Accordingly, I am satisfied that the defendant was in
anticipatory breach of the agreement as at the end of April 2004 and that
the plaintiff was entitled, as he did, albeit verbally, to terminate the
agreement of sale.
Claim for Pre-estimated Damages and Claim for Refund
In terms of clause 7.1.3 of the agreement of sale, in the event of
any material breach by the plaintiff, the defendant would have been
entitled to cancel the agreement and claim damages, retaining any
payments made as security until the quantum of such damages had been
established. In view of my finding that the plaintiff was not in breach of
his payment obligations, the defendant’s claim for pre-estimated
damages cannot be sustained and must therefore be dismissed. For the
sake of completeness, however, I should point out that the approach
adopted by defendant’s counsel in his closing submissions, i.e. applying a
single exchange rate of US$1 to ZW$100,000 as an average rate in
calculating the expenditure incurred by the defendant after April 2004, is
9
HH 124-2012
HC 10764/04
as unhelpful as it is untenable. There is no reference to official banking
rates applied at the relevant time, and I cannot accept that there was any
average rate of exchange applicable to the expenditure incurred over the
entire period in question, i.e. from November 2004 to July 2006.
As regards the plaintiff’s claim, his original claim in September
2004 was for payment in Zimbabwe Dollars. This was amended at the
commencement of the trial to one sounding in United States Dollars.
Counsel for the defendant submits that this amendment was improper
because no explanation was proffered as to why it was sought. He
further contends that the change in currency from Zimbabwe Dollars to
United States Dollars amounts to a change in the cause of action and that
this new cause of action has now prescribed since 2004. With great
respect, I see very little to commend these arguments. The explanation
for the amendment of the plaintiff’s claim to a currency presently in use
was quite obvious. There would have been no point in the plaintiff
persisting with a claim sounding in an inoperative currency. Moreover, it
cannot validly be argued that a change in the currency of claim entails
the institution of an entirely new cause of action. In the circumstances of
this case, the cause of action remains the same and cannot be said to
have prescribed merely because it is expressed in a currency that is
different from the one in which it was originally instituted.
Having said that, I must also declare my great dissatisfaction with
the submissions filed by counsel for the plaintiff. They contain no attempt
whatsoever to substantiate the claim for US$42,000 by way of refund, it
being baldly asserted that the plaintiff is entitled to two-thirds of the
current valuation of the completed property because he had paid
approximately two-thirds of the original purchase price. This approach
entirely ignores the interest component stipulated in the agreement of
10
HH 124-2012
HC 10764/04
sale. At the end of the day, it would appear that neither the plaintiff nor
the defendant is in any position to provide a proper calculation of the
total amount, inclusive of capital and interest, that was due under the
agreement.
Given these deficiencies in the evidence and submissions before
me, I am unable to adopt the proposed approach of computing the
plaintiff’s claim as a proportion of the present value of the property, i.e.
US$63,000. The only other approach that seems to present itself is to
award the plaintiff a refund of the total amount that he actually paid in
Zimbabwe Dollars (ZW$58,536,774) converted to United States Dollars,
applying to the ten payments (from September 2009 to April 2004) the
appropriate exchange rate prevailing at the time that each payment was
made. As a matter of procedure, the plaintiff’s claim should be quantified
by way of a chamber application, filed on notice to the defendant,
enabling it to respond should it wish to do so.
In the result, judgment is entered in favour of the plaintiff as against
the defendant as follows. It is ordered that:
1. The defendant shall repay the plaintiff the equivalent in United
States Dollars of the sum of ZW$58,536,774 (to be computed and
quantified in the manner set out in this judgment) together with
interest thereon at the prescribed rate, calculated from the date of
the summons to the date of payment in full.
2. The defendant shall pay the costs of suit.
Legal Aid Directorate, plaintiff’s legal practitioners
Kawonde & Partners, defendant’s legal practitioners